Progress billing for small contractors: how to invoice by stage of a job

Progress billing means you invoice a job in parts as the work moves forward, instead of waiting until the end. For small contractors, remodelers and trades, it keeps cash coming in while you pay for materials and crews. This guide covers how to split a job into billing stages, how to show deposits and change orders on each progress invoice, what retainage is, and a worked example you can copy.

Key takeaways

  • Progress billing splits the contract price into stages (for example deposit, rough-in, install, final), and you send a progress invoice when each stage is done.
  • Agree the stages, their amounts and what counts as "done" in the contract before work starts. The stages should add up to exactly 100% of the price.
  • Every progress invoice should show the contract total, approved change orders, what was billed and paid before, this invoice and what is left, so the client can check it in one glance.

What is progress billing?

Progress billing is a way of invoicing a job in stages. The contract price is divided into parts, each tied to a stage of the work, and the contractor sends an invoice as each stage is finished. Each of those invoices is called a progress invoice.

It is the normal way to bill anything that takes more than a few days: remodels, additions, roofing, electrical and plumbing work on new builds, landscaping projects and most commercial jobs. The alternative, one invoice at the end, means you pay for materials, crews and subcontractors for weeks before seeing any money.

Two terms come up a lot:

How do you set up billing stages for a job?

Set the stages when you write the estimate or contract, not when the first invoice is due. Good billing stages are:

  1. Easy to see. "Cabinets and countertops installed" is clear. "Phase 2" is not.
  2. Matched to your costs. Stages where you buy expensive materials or bring in a subcontractor should carry enough of the price to cover them.
  3. Few. Three to six stages is plenty for most small jobs. Each one is an invoice, a check and a conversation.
  4. Exactly 100%. Write each stage as a percentage and an amount, and check they add up to the contract price.

Some states limit how large a deposit a contractor can ask for on home improvement work, and some require specific wording in the contract. Check your state's rules before you set the deposit stage.

Example only. Billing stages for a $48,000 kitchen remodel.
StageShareAmountBilled when
Deposit10%$4,800.00Contract signed
Demolition and rough-in25%$12,000.00Rough-in inspection passed
Cabinets and countertops35%$16,800.00Cabinets and tops installed
Finish and walkthrough30%$14,400.00Final walkthrough signed off
Total100%$48,000.00

What should a progress invoice show?

A client paying in stages wants to know three things: what this invoice is for, how it fits the whole job, and how much is left. A clear progress invoice carries:

An example progress invoice

Here is the second invoice for the kitchen above, after one change order was signed. Example only: the job, amounts and numbers are made up.

Example only. Progress invoice 2, kitchen remodel, contract 1187.
LineAmount
Stage 2: demolition and rough-in (25% of contract)$12,000.00
Change order 1: four extra outlets on the island$650.00
This invoice$12,650.00
Example only. Contract summary on the same invoice.
Original contract$48,000.00
Approved change orders$650.00
Revised contract total$48,650.00
Billed before this invoice (deposit)$4,800.00
This invoice$12,650.00
Left to bill on the contract$31,200.00

The client sees the stage in the contract's words, the change order they signed, and that $31,200 is still to come. Nothing needs explaining on the phone.

How do change orders fit into progress billing?

Get every change order in writing, with the price, before doing the work. Then decide in the change order itself how it is billed: with the next stage (as in the example), as its own invoice, or with its own deposit if it needs materials up front. Never fold a change order into a stage amount without a separate line. If the stage total no longer matches the contract, the client's first question will be why.

What is retainage in construction billing?

Retainage (or retention) is a part of each progress payment that the client holds back until the job is finished, as security that the work will be completed and fixed if needed. It is common on commercial jobs and with general contractors paying subcontractors, and the percentage is set in the contract. If your contract has retainage, show on every invoice the amount held back so far, and send a separate invoice for the retained amount when the job is complete and accepted. Some states limit how much retainage can be held or set when it must be released, so check your state's rules.

Larger commercial jobs may also ask for a pay application with a schedule of values: a list of every part of the work with its value and the percentage complete. Many use the AIA G702 (Application and Certificate for Payment) and G703 (Continuation Sheet) forms for this. The idea is the same as the stages above, in more detail.

Common progress billing mistakes

How Orderseam helps with progress billing

Orderseam Invoicing lets you bill lines by stage of a job, by the hour or by unit on one invoice, ask for a deposit, and add fields of your own such as Job site or Contract no. You preview the invoice before it goes out, then send it by email or as a PDF, and the client opens it on a private link with no sign-in. If you connect your own Stripe account, the invoice has a Pay now button for card or bank, the money goes straight to you and Orderseam adds no fee. Reminder emails go out on the days you choose, before and after the due date, once you turn them on, and payments are recorded so "Paid" shows only when the invoice is paid in full. Retainage and contract summaries are not built in yet, so for now you write them as notes on the invoice.

Common questions

What is progress billing in construction?
Progress billing is invoicing a job in stages as the work moves forward. The contract price is split into parts tied to stages such as deposit, rough-in, install and final, and the contractor sends a progress invoice when each stage is finished.
What should a progress invoice include?
The job name or address, the contract number, the stage being billed in the contract's words, any approved change orders on their own lines, a summary of the contract total, what was billed before and what is left, the due date and how to pay.
What is retainage on a progress invoice?
Retainage is a part of each progress payment that the client holds back until the job is finished, as security that the work will be completed. The percentage is set in the contract, and the retained amount is invoiced separately once the job is complete and accepted.